C-65.1, r. 5 - Regulation respecting construction contracts of public bodies

Full text
48. If a contract related to a building involves an expenditure equal to or greater than $3,000,000 and the proposed change order increases the total value of the changes by more than 10% of the initial value of the contract, the public body may issue the change order or any subsequent change order only if the public body confirms to the contractor that the public body has the money necessary to perform the change.
O.C. 532-2008, s. 48; O.C. 873-2008.